Category: T3 News
Dear Sirs, We would like to inform you that during the night from Thursday to Friday 9/10.03.2023 we will be taking noise measurements during the works at the T3 construction site. The measurements will be carried out throughout the night and the measuring
T3 works status - 13.02.2023 In January, we completed the installation of the sheet piles of the north return wall and the closing quay. We also proceeded with the installation of wailing beams and the stabilization of the sheet pile wall by installing flap
In order to ensure transparency and accessibility of information on the implementation of the T3 project at all stages, we would like to inform you of the opportunity to submit complaints and grievances in connection with the construction of the new
Work on the construction of the new T3 terminal. At the moment, dredging work is underway on the water construction site, in the area of the future T3 quay port basin. The work is being carried out with two suction and dredging machines, each capable of
On 28 November 2022, Baltic Hub (formerly known as DCT Gdańsk), the operator of the largest container terminal in the Baltic Sea, ceremoniously kicked off construction of its third deep-water Terminal - T3 in the presence of the Secretary of the State in the
23.09.2022 - it was an important day for DCT! Representatives of DCT Gdansk and the Port of Gdansk met today at the Harbour Master's Office with Councillors of the Stogi and Przeróbka Districts, our closest Neighbours. This was another of our
DCT Gdansk Prepares for Future Growth and Expansion with Purchase of Semi-Automated RTG Cranes DCT Gdansk, the largest container terminal in the Baltic Sea and a member of the PSA Group, has placed an order for 10 new Semi-Automated
DCT Gdańsk, the operator of the largest container terminal complex on the Baltic Sea, has signed a contract for the construction of the third deep-water terminal known as T3. The contract is signed with a consortium of Budimex S.A. and Dredging